Image
image
image
image


Project: John F. Kennedy Airport Runway 13R-31L Reconstruction & Access Improvements

Client: Tutor Perini Corporation Peekskill, New York


At a construction cost exceeding $200 million, Tutor Perini Corporation is improving the longest runway in the U.S. at one of the country’s busiest airports.

The project includes removing and resurfacing 2-1/2 miles of main runway, installing new lighting & navigation aids, adding and reconfiguring taxiways, and providing all drainage, electrical, and other infrastructure work as needed for a complete project.

The schedule meticulously incorporates more than twenty individual “stages” spread over more than thirty major areas. Operations require extremely precise coordination among construction forces, security, FAA and the Port Authority of New York and New Jersey on a continuous basis.


Click image for closeup view Click image for detail










image


image
image